The importance of proper planning for stream crossings cannot be overstated. If stream crossings are not planned and located before road construction begins, you have set the stage for serious problems in the future, including unintended damage to other resources. Requirements for stream crossings vary from State to State. Often a permit is required; check with the water division of your local natural resources agency. This section covers the simple designs and installation methods for culverts and fords. If you have fish in your stream, also see the section on Protecting Fish Habitat. When selecting the best method to build a road across a stream, the following factors must be considered: |
|
| Stream size | |
| Debris potential | |
| Foundation conditions | |
| Construction cost | |
| Maintenance costs | |
| Road use and life. |
|
| Three methods are recommended for crossing a
stream: bridges, pipe culverts, and fords. Water bars, broad-based dips, and open top and
pole culverts should never be used to cross streams. These methods are used to improve
drainage (see the section on Road Drainage Methods). Bridges are not covered here as their construction and design are beyond the scope of this guide. Portable bridges have been widely used in temporary and permanent applications, and are available from several manufacturers. Consult a professional engineer if you are considering a bridge. |
|
Pipe culverts are used primarily to channel water across roadways from uphill drainages or roadside ditches. Spacing would be the same as for water bars (see Water Bars under Road Drainage Methods for spacing). Historically, pipe culverts were steel or aluminum; however, polyurethane culverts have recently been introduced. These double wall constructed pipes are lighter, easier to handle, and can be cut to length with a handsaw. They may be worth considering, if the price is comparable. Use no smaller than a 15-inch pipe (Helvey and Kochenderfer 1988). If there is evidence of a defined stream channel, use at least an 18-inch pipe. A drainage table provides help in determining the proper size culvert (Tables 8 and 9). An example of how to use the table is provided in the box; however, it is generic. Table 10 can also be used to determine proper culvert size and is easier to use (Helvey and Kochenderfer 1988). The method in Table 10 was developed for Appalachian forests. |
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
If you need help determining the size of a culvert, your local land con-servation department or a private consultant may be of assistance. Make sure they do not size the culverts for a 50- or 100-year storm, unless that is your desire. For low standard or tem-porary roads, a flood frequency of 25 years can be used. |
|
![]() Figure 16. It is important to plan for the failure of a stream crossing, to reduce the amount of sediment that would enter the stream channel should the crossing fail. (Redrawn from Furniss et al. 1991, p. 310) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stream crossings, such as culverts, can be considered dams that are designed to fail. The risk of culvert failure is substantial for most crossings, so how they fail is critical. In the upper sketch in Figure 16, the crossing has failed and the road grade has diverted the stream down the road, resulting in severe erosion and downstream sedimentation. Such damage to aquatic habitats can persist for many years. Stream diversions are easy to prevent, as illustrated by the lower sketch, in which the road grade was such that a failed crossing caused only the loss of some road fill (Furniss et al. 1991). |
![]() Figure 17. A cross section of a culvert at A-A shows the recommended structure of fill material installed around a culvert pipe. (Redrawn and adapted from Figures 6-5 and 6-6, Wisconsin Department of Natural Resources 1995, p. 26) |
| Culverts should be installed as the road work progresses. The culvert and its related drainage features should be installed in the following order: | |
| 1. | Place debris and slash to be used as a filter system, if needed. |
| 2. | Construct sediment ponds, if needed. |
| 3. | Complete downstream work first, such as energy dissipating devices and large rock riprap. |
| 4. | Route stream around work area until pipe is installed. |
| 5. | Construct pipe inlet structure. |
| 6. | Install culvert pipe. |
| A culvert inlet should be placed on the same
level as the stream bottom. In some instances where the culvert inlet has to be lower than
the drainage gradient, a drop box can be constructed. This box, which is a place for
sediment to settle out before water enters the culvert, needs frequent maintenance. Install culvert pipes as near as possible to the gradient of the natural channel and so there is no change in the stream bottom elevation (Figure 17 top). Culverts should not cause damming or pooling. Seat the culvert on firm ground and compact the earth at least halfway up the side of the pipe to prevent water from leaking around it. Pipe culverts must be adequately covered with fill; the rule is a minimum of 12 inches or half the culvert diameter, whichever is greater (Figure 17 bottom). |
![]() Culverts not installed at the same level as the stream cause water to back up. |
| If adequate cover cannot be achieved, then an arch pipe or two small culverts should be installed. The cover must also be compacted to prevent settling in the road. Debris-laden material should not be used to cover pipe culverts. |
![]() Figure 18. Use stabilization practices on soil exposed at stream crossings during construction, until the soil is permanently stabilized. (Detail A-A redrawn and adapted from Figure 6-13a, Wisconsin Department of Natural Resources 1995, p. 35) |
|
||||||||||||
![]() |
![]() |
|
|---|---|---|
| Undersized culverts can become plugged with sediment | A culvert not installed at the existing stream gradient can degrade the stream channel. |
![]() Figure 19. Install riprap to prevent erosion at the inlet to a culvert pipe. |
|
||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
|||||||||||||||
| Return to "A Landowner's Guide to Building Forest Access Roads" Table of Contents |