Approaches to Working with Disaster Relief
Organizations
6.1 Chapter
Summary
When the impact of a disaster is beyond what local authorities can
manage, communities may need to seek assistance from the State or Federal
Emergency Management Agencies (SEMA and FEMA, respectively). Impacted areas may
be declared a State or Federal major disaster or emergency. The declaration
process follows the pattern of local authorities contacting SEMAs, the SEMA
contacting the Regional FEMA offices, and Regional FEMA offices contacting the
National FEMA office, which ultimately will contact the President.
After an area has been declared a major disaster or emergency, all
appropriate parties are notified the kinds of assistance available are
identified, and the areas included in the declaration are established.
A number of multi-agency teams work together to assess the impact
and needs of the disaster. One team consisting of Federal, State and local
representatives, completes a Damage Survey Report (DSR). It is critical that
the local arborist or forester is involved on this team so that the impact on
the tree resource is identified. The Interagency Hazard Mitigation Team (IHMT)
studies the disaster area and recommends hazard mitigation options to be
implemented to reduce future disaster impacts.
For a community to receive any funding for tree care activities,
it must demonstrate a commitment to the tree resource. This commitment may be
shown by having a tree ordinance, a community forest management plan or
inventory, a staff forester, or by having Tree City USA status. Funding that
comes as a result of a declaration is sought for a variety of uses. To obtain
funding for the tree resource, it is important to be prepared.
6.2 Chapter
Outline
I. Introduction
II. The Declaration Process
III. Federal Disaster Declaration and Activities
IV. FEMA Disaster Assistance Program
V. Dealing with the FEMA for Public Assistance
VI. Developing a Disaster Survey Report
VII. Disaster Survey Report Example
VIII. Hazard Mitigation
IX. For More Information
6.3
Introduction
When a disaster occurs, the initial response and recovery
activities are emphasized at the local level. Local police, fire and public
works departments work cooperatively to get the situation under control. Under
certain circumstances, additional help will be needed. Local authorities may
contact their State Emergency Management Agency (SEMA) for this assistance.
SEMA will then determine, either through an actual site visit or a phone call,
whether the area needs to be declared a disaster. if the area needs to be
declared a disaster, SEMA will go to the Governor for such a declaration. In
some cases, the disaster situation may exceed the capabilities of state and
local forces, and the Governor may request that the President declare a "major
disaster" or an "emergency."
A "major disaster" is defined as "any natural catastrophe
(including any hurricane, tornado, storm, high water, wind-driven water, tidal
wave, tsunami, earthquake, volcanic eruption, landslide, mudslide,
snowstorm, or drought), or, regardless of cause, any fire, flood, or explosion
in any part of the United States, which, in the determination of the President
causes damage of sufficient severity and magnitude to warrant major disaster
assistance under this Act to supplement the efforts and available resources of
states, local governments, and disaster relief organizations in alleviating the
damage, loss, hardship, or suffering caused thereby." (FEMA, 1990).
An "emergency" is defined as "any occasion or instance for which,
in the determination of the President, federal assistance is needed to
supplement state and local efforts and capabilities to save lives and to
protect property and public health and safety, or to lessen or avert the threat
of a catastrophe in any part of the United States." (FEMA, 1990).
6.4 The Declaration
Process
The actual process of declaring an area to be a major disaster or
an emergency involves a number of steps. A declaration request may be denied at
the state or federal level, the usual reason being that there is not enough
damage. Note: Denials can be appealed. The following is a listing of the steps
involved after a disaster has occurred when an area seeks state or federal
disaster assistance, or both (Personal communication, Powers and Ogan,
1992):
A. Event occurs.
B. Local response. Local authorities (city,
county, police, fire, etc.) respond to the disaster with activities such as
clearing debris, searching for victims, and immediate repairs. If local
authorities can handle the disaster with their own resources, they will not
seek further assistance (process ends here). If not,
C. Local authorities contact SEMA. (See Chapter 9,
Section 9.7, "State Offices Responsible for Disaster Operations.") SEMA will
respond in person or by phone and complete a preliminary damage assessment
(PDA). A PDA usually occurs as soon as possible. (Note: If damage is so severe
and obvious, a PDA may not be necessary and the area may be declared a disaster
automatically. The damage left behind by Hurricane Andrew, of 1992, is an
example of an area that was automatically declared.) if a state declaration is
warranted, SEMA will go to the Governor with a request. The request may or may
not be accepted by the Governor. If it is not accepted, the local area may
appeal and submit another request. If the request is accepted, the Governor
will declare the area a State disaster and the area will receive State relief.
In certain cases, the damage may exceed what the State can do to assist, and
the State will seek Federal assistance. If so,
D. SEMA authorities contact regional Federal
Emergency Management Agency (FEMA) offices (see Chapter 9, Section 9.6, FEMA
Offices). The SEMA inspectors will share their findings with the regional
Federal Emergency Management Agency (FEMA) office, and that regional FEMA
office will submit a recommendation to the National FEMA office for a
declaration. The National office may or may not support the recommendation. If
they do not support the recommendation, the State may appeal. The appeal will
usually indicate damage figures that support the fact that there is more damage
than initially reported. If this appeal is again denied, the State can appeal
directly to the President. If the National FEMA officials support the
recommendation, they will then go to the President and recommend that the area
be declared a major disaster or an emergency.
6.5 Federal Disaster Declaration and
Activities
After the President declares an area to be a major disaster or an
emergency, all appropriate involved parties are notified (governor(s), members
of Congress and Federal departments or agencies). The kinds of assistance that
will be made available and the counties or other political subdivisions that
are eligible to receive assistance will then be identified.
A FEMA official will be appointed as the Federal Coordinating
Officer (FCO) for the area. Based on initial PDA's and other information, the
FCO will make an appraisal of the type of relief most urgently needed. The role
of the FCO is to coordinate all Federal disaster assistance programs and to
ensure that appropriate action is taken to help affected citizens and public
officials receive the assistance to which they are entitled.
The FCO also receives assistance from other Federal agency
disaster assistance specialists by forming an emergency support team(s). The
FCO will also establish a temporary Disaster Field Office within the area that
was affected to serve as a central location to coordinate the relief and
recovery effort.
Additionally, after the area is declared a major disaster or an
emergency, the Governor and the Regional FEMA Director will execute a
FEMA-State Agreement. This Agreement identifies the manner in which Federal aid
will be made available. it includes the following: the areas within the State
that are eligible for assistance, the division of costs among Federal, State
and local governments; the official period of duration to be recognized for the
major disaster or emergency; and any other conditions of assistance.
6.6 FEMA Disaster
Assistance Program
Under the authority of the Stafford Act (Public Law 100-707), FEMA
provides public and individual assistance for recovery and reconstruction
projects after a Presidentially declared disaster or emergency declaration. To
receive this assistance, the state is required to prepare a State Hazard
Mitigation Plan (Section 409). Types of assistance include (Florida Department
of Community Affairs Division of Emergency Management, 1994):
- Public Assistance (Section 409)
As part of
the Public Assistance Program, funding for appropriate cost-effective hazard
mitigation measures related to damaged public facilities is available to local
government.
- Individual and Family Grant Program (Section 411)
The individual and Family Grant (IFG) Program can be used by individuals
to fund limited hazard mitigation activities. The IFG Program provides grants
to states for making subgrants to individuals or families for serious and
un-met disaster related needs. Although the amount awarded to a family is
fairly limited, the funds may be used to take minimum measures required to
protect homes against the immediate threat of damage or further damage.
- Hazard Mitigation Assistance Program (Section 409)
The Hazard Mitigation Assistance Program provides funding assistance to
states and local governments to reduce vulnerability from recurring or
potentially severe hazards by supporting hazard mitigation planning activities.
The focus of the program is on hazard mitigation plans or the updating of
previous plans.
- Hazard Mitigation Grant Program (Section 404)
FEMA provides financial support to implement cost-effective mitigation measures
that are consistent with measures identified in the 409 Plan. The state is
responsible for the management and administration of the programs.
Funding for the replacement of trees lost during a disaster may be
funded under the Public Assistance Program of the Hazard Mitigation Grant
Program. The Hazard Mitigation Grant Program usually requires match funds and
is funded by a small percentage of total federal dollars allotted to the
disaster: hence, the amount of funding available is very limited.
6.7 Dealing with the FEMA for Public
Assistance
For the purpose of this mitigation document, the focus of this
section will be on the assistance available for trees as a community resource.
For information regarding other types of assistance, refer to the document
entitled, "Disaster Assistance Programs: A Guide to Federal Aid in Disasters."
(FEMA, 1990.)
In order for a community or eligible group to receive any type of
assistance from FEMA, they must submit a Notice of Interest (NOI) within 30
days after the area is designated eligible for assistance. The NOI establishes
that the community is in need and would like to receive assistance from FEMA.
Estimates of reimbursable tree damage and the amount of funding allowed will be
calculated through the Disaster Survey Report (DSR) process and unit costs set
by FEMA.
FEMA's unit costs are set nationally and may need adjusting for
the disaster area. With the South Florida's Hurricane Andrew Disaster the
original amount of $100.00 per replacement tree and planting was far too low to
cover replanting of adequate trees. Dade County's Tree Ordinance, which
communities in the county are required to base their ordinances on, requires
that at least eight foot planting stock be used. This size requirement, along
with the rocky soil of South Dade County, made planting costs much higher than
normal. Utilizing proper documentation (past planting costs and proof of
ordinance enforcement) the reimbursable amount for replacement trees was
increased to $200.00. Also, the ordinance required replacement of lost canopy;
with large trees being replaced with two or three small trees. Note: It is
very important that local personnel be aware of items that FEMA will reimburse
for and the amounts that are paid so that these types of adjustments can be
made as soon as possible. FEMA personnel are sometimes activated retirees
and they may not be aware of recent changes, or may lack specific knowledge in
tree-related information.
A team made up of a local, a state and a FEMA representative will
work together to assess the impacted areas and develop a DSR. This assessment
provides FEMA and SEMA with an estimated budget needed for the relief
and recovery effort. Note: The choice of the local and state representatives on
a DSR team is critical. It is that local person's responsibility to show
effectively and efficiently where the damage exists and the extent and cost of
the damage and to describe what plans have been developed to correct the
problem. It is also important to have personnel that are informed of the type
of damage that has occurred. When dealing with tree damage and replacements,
the local personnel should be knowledgeable of trees. It also helps if the
state representative is also knowledgeable of trees and tree damage and can
offer an "unbiased" assessment of the tree damage. judgment calls may need to
be made on the tree's survivability.
In certain situations, the city forester may be actively involved
in storm response activities and may not have time to serve on the DSR team. In
that situation, a community can demand that FEMA provide the assistance of a
tree-assessment team made up of people who are tree experts or FEMA consultants
on contract. For example, during the Rochester ice storm of 1992, the city
forester was not involved in the DSR team. The DSR team consisted of a FEMA
consultant, a USFS urban forester, a computer engineer from the Army Corps of
Engineers, and a local highway construction supervisor who knew the roads in
the damaged area (Ossenbruggen, 1993) These DSR's are reviewed and submitted by
the state to the FEMA regional director for approval. If approved, the state
will serve as the grantee for the program with complete program management and
financial responsibilities.
NOTE: During the Hurricane Andrew incident in South Florida, the
Florida Division of Forestry was able to place a liaison at FEMA's Public
Assistance headquarters to assist the agency in developing policies concerning
trees. This proved valuable in setting replacement values, decisions concerning
remedial pruning, salvaging of damaged trees, and replacement species
selection.
In considering the tree resource during a DSR assessment, it is
vital for the public assistance person to recognize a community's commitment to
tree management. If a community is not committed to tree management and is not
perceived as being committed to managing its trees as a resource, inspectors
may not allow tree costs to be covered. Indications of a community's commitment
may include, but are not limited to, the existence of a community tree
ordinance designation as a Tree City USA community, the existence of a
management or maintenance plan for their resources, a completed tree inventory,
the presence of a community forester or arborist, or documents showing previous
tree replacement or maintenance because of other natural occurrences.
Communities should note the following two key points:
- A community must show commitment to the tree resource through
some form of a dedicated tree care program. If this is not the case and the
community recognizes the need and importance of a tree management program, the
community may be able to show a dedication to pursuing the effort and therefore
receive assistance.
- A local community forester or arborist must be involved in the
DSR. In doing so, the person will serve as the expert in describing the
situation in terms of numbers of trees lost, removed, damaged, requiring proper
pruning, and numbers of trees to be planted.
Often during a DSR with smaller communities, the focus is not on
damage and loss to the tree resource. In fact, tree resource information may
not be included in the initial DSR. These DSR's can be amended. Therefore, if
commitment is shown for managing the tree resource and figures indicating tree
loss and damage are generated, the DSR can be modified to include them. Once
again, the bottom line to getting assistance for the tree resource is: A
community must show commitment to maintaining its tree resource.
The type of assistance available to communities that show a
commitment to managing their tree resource falls under the category of "Public
Assistance" for "Emergency Work." Emergency work consists of work involving
debris clearance, trees, buildings, bridges, and any emergency protective
measures by police and fire officials. Generally, the cost-share for this work
is 75/25. Federal assistance covers 75 percent; state assistance matches at 25
percent. Sometimes, the state match will be divided between the state and local
governments on a 12.5/12.5 basis, in other cases, the state will cover the full
25 percent. Note: For Hurricane Andrew in 1992, Federal Assistance covered 100
percent of the costs.
6.8 Developing a Disaster Survey
Report
occasionally, there may be special considerations to the disaster
due to the location of the disaster. In the cases of Hurricane Hugo and
Hurricane Andrew, the potential of wildfires and their threat to improvements
was increased beyond the resources of local and state wildfire fighting
agencies. State agencies submitted DSRs to FEMA requesting additional work
force and equipment to meet the increased workload. In both cases, the DSRs
were approved and temporary resources were provided. Note: "Temporary"
resources are still being used in South Florida and the North Carolina because
of the hurricanes. South Florida's urban forest resources were damaged to such
an extent that the Florida Division of Forestry requested, and was granted,
additional urban foresters to plan and supervise the replanting process. (See
Chapter 8, "Notes on Hurricane Andrew.")
The following outline is provided to help in developing these
types of DSRs. (The situation that the additional assistance is needed for is
referred to as the "issue.")
ISSUE: PUBLIC
ASSISTANCE FOR RECOVERY PROJECT
I. BACKGROUND: Summary
of how the disaster event effected the resource that the additional assistance
is needed. II. WORK ELEMENT: Summary
of actions that need to be taken to rectify the situation.
A. LEAD
AGENCIES: List of agencies that will be the major contributors to the
recovery process.
B. FUNDING:
List of funding sources for recovery actions including FEMA.
C. SCHEDULE:
A brief statement stating the beginning and end of the requested project.
III. INTRODUCTION: A description of the
benefits and condition of the resource before the disaster and how the disaster
affected the
resource. IV. ORGANIZATION, OPERATION,
AND FISCAL MANAGEMENT
A. ORGANIZATION
AND STAFFING: A brief description of the agency's organizational structure
and where the
requested
project and personnel fit into the organization.
B. POSITION
DESCRIPTION OF REQUESTED PERSONNEL: A detailed description of the duties of
the requested
personnel.
(it is important to cover all duties of the positions because this section is
used by FEMA to review the
effectiveness
and progress of the personnel.)
C. PROJECT
DURATION: Estimate of the length of recovery process that additional
resources will be needed.
D.
PRIORITIZATION OF PROJECT ACTIONS
1.
IMMEDIATE ACTIONS (FIRST PRIORITY) List of the immediate
actions that need to be taken at the beginning
of
the workplan.
2.
INTERMEDIATE ACTIONS (SECOND PRIORITY)
3.
LONG-TERM ACTIONS (THIRD PRIORITY)
E. BUDGET
INFORMATION: A detailed budget showing all estimated costs for the duration
of the project including
equipment
(purchased and leased), personnel costs, and contractual expenses.
1.
PERSONNEL: Estimated salaries for all additional
personnel for the duration of the project.
2.
EXPENSE: Detailed estimate of the cost of purchased and
leased equipment for the duration of the project.
3.
CONTRACTUAL: Detailed estimate of contractual expenses.
4.
TOTAL PROGRAM COST
Note: It is important to emphasize that the requested project is
within the normal operation of the agency requesting assistance but the
disaster has created a situation that the agency's existing resources can not
handle.
6.9 Disaster Survey Report
The following is an example of an approved DSR submitted to FEMA,
written by Gene Dempsey and James B. Harrell, Cooperative Forestry Assistance
Supervisor, Florida Division of Forestry. Utilize this example as a model when
writing Disaster Survey Reports:
FLORIDA DEPARTMENT OF AGRICULTURE AND CONSUMER
SERVICES
DIVISION OF FORESTRY
HURRICANE ANDREW URBAN REFORESTATION ISSUE
ISSUE: PUBLIC ASSISTANCE FOR RE-ESTABLISHMENT OF
URBAN AND COMMUNITY TREES
BACKGROUND: Hurricane Andrew severely damaged the
urban tree resources on both public and private lands in Dade, Monroe and
Broward Counties and parts of Collier County. In the direct path of the
hurricane, the estimates of trees destroyed (uprooted or broken off) or
severely damaged (requiring extensive corrective trimming of major limbs) range
from 60 to 90 percent of the pre-hurricane tree canopy. The immediate removal
of the downed tree debris, plus the subsequent removal of trees that later die
due to the indirect causes of physiological stress and/or insect and disease
infestations, will essentially eliminate the urban tree canopy and denude the
heaviest hit area of trees. immediate action is needed to insure that trees are
replanted in urban areas and that the urban forest that develops does not
constitute a safety hazard to the general public.
WORK ELEMENT: A proactive campaign of technical
assistance beyond the normal capabilities of the Division of Forestry is
necessary to insure the replanting of appropriate tree species on both public
and private lands. The magnitude of the reforestation effort in the devastated
area will require additional manpower and equipment to supplement current
Division of Forestry resources. Total program measures to restore the
pre-hurricane tree canopy should include:
- Assist community leaders and private landowners with the
selection of appropriate tree species, eliminating exotic pest tree species and
those species prone to wind damage.
- Disseminate information dealing with proper planting and
location techniques.
- Provide information and education materials on the
identification of hazardous trees created by Hurricane Andrew.
- Assist community leaders with the development of plans
for continuing tree care and maintenance programs.
- Educate the public on:
- chainsaw safety
- safety hazards when clearing debris
- debris disposal
- equitable vendor prices
- selecting a qualified arborist or tree care
professional
- selecting quality nursery stock
- benefits of urban trees and the advantages of a
healthier and safer urban forest.
- Host tree care workshops for private citizens.
- Conduct a study to determine the effects of
hurricane-force winds on common South Florida tree species.
- Promote and coordinate volunteer tree planting programs.
|
LEAD AGENCIES: Florida Department of Agriculture
and Consumer Services (FDOACS) Division of Forestry, Florida Cooperative
Extension Service, Florida Urban Forestry Council
FUNDING: FDOACS Division of Forestry; Florida
Cooperative Extension Service; FEMA
SCHEDULE: Begin immediately and continue through
September 30, 1994.
Hurricane Andrew Urban Reforestation
Plan (Click to view)
6.10 Hazard
Mitigation
Assistance may also come to the community in the form of hazard
mitigation. An Interagency Hazard Mitigation Team (IHMT) made up of individuals
from state and federal agencies, including FEMA, SEMA, Soil Conservation
Service, U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, USDA
Forest Service, Federal or State Highway Departments, Economic Development
Administration, the National Weather Service, the State Department of Natural
Resources, and the U.S. Geological Survey, as well as others, work together to
identify and make recommendations for activities and ways to reduce damage in
future disasters. Depending on the Hazard Mitigation Funding that is available,
communities may receive funding for one or more of the IHMT's
recommendations.
Types of recommendations by the IHMT regarding the tree resource
may include one or more of the following (please note, the list below is not
all-inclusive, nor listed, in order of importance):
- Education of local authorities, tree care workers, urban
foresters, arborists, citizens, and volunteer groups about urban forest
management and about the need to properly plant, prune and maintain
trees.
- Identification of trees that need to be pruned to reduce
potential limb failure in future storms.
- Maintenance practices that will improve the overall health and
quality of the tree for future disasters.
- The development of community tree ordinances.
- The completion of an inventory of the tree resource and a
management plan based on information from the inventory.
- Identification of options for wood waste utilization or
methodologies for the least cost disposal.
- The development of a hazard mitigation plan that considers the
tree resource.
Hazard Mitigation Funding is limited. The amount of funding is
determined by taking ten percent of the amount of funding that-was received for
the area for use for permanent restorative work. Thus, if an area is to receive
$1 million for permanent restorative work as a result of a disaster, then only
$100,000 would be available for hazard mitigation activities. These activities
are not limited to the tree resource and may involve housing on floodplains,
bridge replacement or restructuring, highway reconstruction, etc. Therefore, it
is important that the activities that are recommended are deemed to be very
important and can be well justified.
6.11 For More
Information
Federal Emergency Management Agency. 1990. Disaster assistance
programs: A guide to Federal aid in natural disasters. Federal Emergency
Management Agency. Washington, D.C. 20472
Florida Department of Community Affairs Division of Emergency
Management, 1994. State of Florida Hazard Mitigation Plan (Draft)
Matheny, N. P., and J. R. Clark. 1991. A photographic guide to
the evaluation of hazard trees in urban areas. International Society of
Arboriculture, Savoy, IL 61874.
Shigo, A. L. 1989. Tree pruning, a worldwide photo guide.
Shigo and Trees, Associates. 4 Denbow Road, Durham, NH 03824-3105.
Contact the nearest State Emergency Management Agency or local
Federal Emergency Management Agency regional office for additional information.
(Refer to Chapter 9, Sections 9.6 and 9.7, for addresses and telephone
numbers.)
Return to:
Table of
Contents |